BROWNSVILLE, Texas — Cameron County residents will get a formal chance Monday to question a proposed rewrite of a federally supported sewer project after county records showed a smaller construction contract, fewer feet of sewer pipe and dozens of addresses removed from the work.

The county has scheduled a public hearing for 5:30 p.m. Oct. 26 in the Commissioners Courtroom at the Dancy Building, 1100 E. Monroe St. Written comments are due to the Planning and Development Department at the same time, according to the county’s hearing notice.

The proposed amendment covers the Central Estates–Praxedis Saldivar first-time sewer project, a Texas Community Development Block Grant job identified as contract CFC24-0004. The county’s amendment packet would reduce planned 8-inch sewer line from 6,030 feet to 5,272 feet. It would also delete 2,635 feet of 15-inch pipe from the performance statement because that pipe size was not used.

The packet lists a preliminary revised project cost of $1,229,918, about 24% below the earlier total. The construction contract would fall by $385,637 to $1,169,918, while the county would retain $60,000 for administration. County officials caution that those amounts remain preliminary and may change with final revisions and approvals.

The most consequential changes are at the property level. The county proposes removing 44 address records because owners declined connections, required right-of-entry forms were not obtained, easements could not be secured, properties were vacant or records were duplicated. Thirteen properties would be added or have addresses corrected after the county identified them and obtained signed entry forms.

The documents do not fully reconcile two sets of counts. The summary and revised performance statement say the project would provide first-time sewer service to 42 households, decommission 41 septic systems and install 25 capped laterals for potential future connections. An engineering justification in the same packet says 42 households were removed from an original group of 83, leaving 41 beneficiaries, and that 24 future stub-outs were installed. The packet also uses “beneficiaries” for people in one table—179 total, including 177 low- or moderate-income residents—while the engineering letter appears to use the term for service connections.

That distinction matters because the amendment is supposed to define what the public grant will deliver. The American Quorum could not verify a current project-specific email address for the named county contact before publication; residents can ask the county to reconcile the 41-versus-42 service count and the 24-versus-25 future-connection count at the hearing.

Texas Department of Agriculture rules require a hearing when a community-development project undergoes a substantial change. The state’s program manual says the process must give residents an opportunity to comment before the amendment proceeds.

People who need disability accommodations should contact the Cameron County Personnel Office at 956-544-0827 at least two days before the meeting. Project questions may be directed to Esther Ballesteros at 956-982-5422. The county says it will consider written comments received by the 5:30 p.m. Oct. 26 deadline before moving forward.

Illustration: AI-generated conceptual image of sewer-line construction; it does not depict this project or a specific Cameron County site.